GENERAL OVERHAUL, CHP plant JINDŘICHŮV HRADEC, CZECHIA

GENERAL OVERHAUL, CHP plant JINDŘICHŮV HRADEC, CZECHIA
Owner's Engineer Design and Studies Installation and Supply Diagnostics
✓ ✓

 

We coordinated the general overhaul of the CHP plant incinerating baled straw. We performed services as the Owner's Engineer for the plant's owner and operator – CEZ Group.

BFS Industry activities:

  • Planning of the scope of the general overhaul of the CHP plant
  • Coordination of procurement of suppliers
  • Supervision and coordination of assembly works
  • Coordination of the process of demonstrating the guaranteed parameters and handover of the work

Scope of the overhaul:

  • Replacement of flue gas filter
  • Replacement of heat exchanging surfaces of economizers and superheaters
  • General overhaul of the turbogenerator
  • Replacement of slag hoppers

Complete overhaul preparation: 01/2016 - 06/2017

Complete overhaul execution: 07/2017 - 08/2017

Technical specifications of the plant:

  • Fuel: Baled straw
  • Electric power output: 5.6 MWe
  • Heat output: 15 MWt