Owner's Engineer Design and Studies Installation and Supply Diagnostics

Our company was responsible for preparing the comprehensive design documentation for the installation of a new electric boiler up to 5 MW for the provision of ancillary services.
We also held the roles of Chief Project Engineer and Project Manager.

BFS Industry activities:

  • Preparation of comprehensive design documentation
  • Engineering design
  • Project management
  • Programming of the automatic control system

Technical specifications:

  • Voltage level: 6.3 kV
  • Electrical power input: up to 5 MW

Location: Caslav, Czechia

Construction: 1/2023 - 7/2024