Our company prepared an implementation study of steam reducing turbine into the CHP plant cycle in Mostek, Czechia.
The study can be used as:
- a foundation for a feasibility study
- a input document for designing
BFS Industry activities:
- Identification of considered options
- Thermodynamic cycle calculation
- Evaluation of 4 different variants of driven agregates (pumps and fans)
- Recommendation of the following actions
Location: Mostek, Czechia
Execution dates: 07/2020 - 09/2020
Technical specifications:
- Considered agregates:
- Feed-water pump 90kW
- Cooling circuit pump 315 kW
- Primary air fan: 315 kW
- Induced draft fan: 160 kW