WATER CONSUMPTION OPTIMIZATION, CHP PLANT KUTNÁ HORA, CZECHIA

WATER CONSUMPTION OPTIMIZATION, CHP PLANT KUTNÁ HORA, CZECHIA
Owner's Engineer Design and Studies Installation and Supply Diagnostics
✓ ✓

We provided the design and installation of the system for reducing consumption of water in the CHP plant. We also designed and completely programmed control system using Siemens PLC S7-1200 platform. Saving of water is achieved by using the water from cleaner processes in the processes with possibility of using polluted water.

BFS Industry activities:

  • Designing project documentation
  • Supply and installation of the technology
  • Programming of control system
  • Commissioning

Location: Kutná Hora, Czechia

Construction dates: 09/2018 - 11/2018

Technical specifications:

  • Reduced consumption of drinking water: 13,9 m3/day
  • Reduced consumption of industrial water: 21,1 m3/day