STEAM TURBINE SPARE PARTS procurement, CHP PLANT KUTNÁ HORA, CZECHIA

STEAM TURBINE SPARE PARTS procurement, CHP PLANT KUTNÁ HORA, CZECHIA
Owner's Engineer Design and Studies Installation and Supply Diagnostics
✓

We specified the scope of spare parts for steam turbine island, managed the procurement process and lead the negotiations with spare parts supplier.

BFS Industry activities:

  • Spare parts specification
  • Procurement
  • Negotiations with supplier
  • Preparation technical parts of the contract

Location: Kutná Hora, Czechia

Procurement: 04/2018 - 01/2019

Expected delivery: 01/2020

Technical specifications of the turbine:

  • Steam turbine power output: 7,4 MWe 
  • Extraction condensing turbine 
  • Admission steam temperature: 400 °C 
  • Admission steampressure: 4 MPa(g)