We provided the designing, permitting and construction of closed cooling circuit for cooling the ancillary equipment in CHP plant. The cooling circuit was integrated into the existing technology. Its commissioning was done with minimum shut-down time of the CHP plant - 4 hours.
BFS Industry activities:
“Brownfield” project
Construction: 06/2015 - 09/2015
Technical specification of the cooling circuit: