Feasibility study for steam pipeline reconstruction

Feasibility study for steam pipeline reconstruction
Owner's Engineer Design and Studies Installation and Supply Diagnostics

Our company prepared a feasibility study for the reconstruction of the existing steam pipeline. Balance calculations and a proposal for a new solution were carried out to meet the current lower heat supply requirements. The study also included an assessment of the technical condition of the existing steam pipeline and a design proposal for a new pipeline.

Technical parameters of the project:

  • Reconstruction of the steam pipeline section: 7 km
  • Design thermal output: 25 MW

Role of BFS Industry in the project:

  • Preparation of the feasibility study